St. Petersburg Sewage Update

 
Consent Order
A proposed consent order between St. Petersburg and FDEP came out this week.

In response to the sewage overflows in St. Petersburg, FL, a draft Consent Order [pdf] has been released by St. Petersburg and Florida Dept. of Environmental Protection. Proposed improvements in the draft include:

  • Increasing the capacity of the Southwest Reclamation Facility (cost $21.7 M)
  • Construct two additional injection wells for disposal of treated sewage cost ($12.2 M)
  • Albert Whitehead Water Reclamaition Facility storage to be increased from 5 to 8 miillion gallons (cost $3.3 M)
  • Sanitary sewer evaluation (cost $.8 M)
  • Repair/replace wastewater system components ($35.5 M through FY21)

To view the draft consent order go here.

Recent Posts

Lawsuit Challenges Trump Administration for Failing to Protect Gulf of Mexico Wildlife from Offshore Drilling...
Written by Dustin Renaud
Thursday, 21 June 2018
Jackson, Miss. – On June 20, 2018, a Draft Environmental Impact Statement (EIS) study for...
Written by Dustin Renaud
Thursday, 21 June 2018
Gazing out at its usually calm waters, one would never know that Pensacola Bay is...
Written by Christian Wagley
Tuesday, 05 June 2018
A Community Engagement Meeting on the flood control project for the Pearl River (One Lake...
Written by Andrew Whitehurst
Thursday, 26 April 2018
On April 19th, Gulf Restoration Network released a new report - “ Oil and Gas...
Written by Raleigh Hoke
Thursday, 19 April 2018
The Mississippi Water Resources Conference happened in Jackson on April 3-4 and provided many presentations...
Written by Andrew Whitehurst
Friday, 06 April 2018
The Yazoo Backwater Pumps project is a 77 year old Army Corps of Engineers’ (Corps)...
Written by Cyn Sarthou
Wednesday, 28 March 2018

SHARE THIS PAGE